Welcome to Hillcroft

A welcoming, family-friendly community

 

Current as at: September 2024

Housing construction and sales

Stage 11: Recent rain has caused a slight delay; however, Stage 11 is due to be completed in the coming month.

Stage 5: Site remediation for Stage 5 is now complete with earthworks to start in the coming weeks.

Stage 4: Stage 4 design, including the new stormwater basin design was submitted to Campbelltown Council this month. Remediation works should start towards the end of this year.

Stage 3C: The detailed design for Stage 3C is progressing well, and construction work is expected to begin later this year.

Dimeny Park: The design has been updated to include Council’s comments and is now with Council for approval.

Latest sales: The latest release of lots for sale was held on 13 July 2024.

 

The project

Hillcroft is a modern, socially mixed community set on 125 hectares in Sydney’s south western suburb of Claymore.

In partnership with the NSW Land and Housing Corporation, Landcom is delivering Hillcroft as an aspirational destination for affordable land and connected lifestyles.

The project includes:

  • 247 new land lots in Stages 1 and 2 (already completed)
  • 463 private homes and 128 social homes in Stages 3 to 6 (currently under development)
  • 330 private homes and 320 social homes in Stages 7 to 13 (to be delivered by NSW Land and Housing Corporation)
  • upgraded social housing
  • improved road and pedestrian connections
  • upgraded open spaces
  • a new town centre, combining shops and community facilities
  • events and skills development programs for the local community
Hillcroft street view
Location

Claymore, 2km west of Campbelltown

Local council area

Campbelltown City Council

Proposed homes

Approximately 1,490 private and social homes (total project), 838 homes to be delivered in Stages 1-6

Community

At Hillcroft, Landcom is committed to building a thriving and engaged community through activities that bring people together to interact and learn. These include:

  • Community-related seasonal and cultural events throughout the year, to drive social connections · Free fitness classes (through Live Life Get Active) that run five days a week during school terms, to improve the health and wellbeing of residents
  • Free fortnightly program of fitness activities (through Ready Steady Go Kids) for primary school students, to improve the health and wellbeing of kids
  • Mental resilience classes for primary school students (through the National Theatre for Children’s Mind Masters Program), to educate about mental health and build resilience and wellbeing
  • A waste education and recycling program (through Keep Australia Beautiful) to educate children on the importance of effective waste practices and embed a sense of caring for and pride in their community
  • A skills exchange program, delivered in partnership with Empowering Growth, to help fund training that supports employment outcomes (e.g. drivers licence applications, TAFE qualifications and certificates).
Hillcroft landcomm video
Landcom Local Voices
New residents (estimated)

4,500 (total project)

Proposed retail area

14,000m²

Delivery timing

2013 onwards, in 13 stages

Community poll

How do you prefer to get community updates?

Timeline

  • Davis Park, Stage 3C and Stage 4 anticipated to begin construction
  • Stage 5 anticipated to be completed
  • Dimeny Park upgrade works anticipated to begin, pending approvals
  • Continued planning and construction of further stages to support future residential development
  • Stage 5 anticipated to begin construction
  • Stage 4 lot sales began (2023)
  • Stage 3C development application approved (2023)
  • Stage 3A and 3B construction completed (2022)
  • Sale of Stage 3 lots continued (2022)
  • Stage 3 lot sales started (2021)
  • Planning for Stages 4-6 continued (2021)
  • Stage 3A and 3B construction continued (2020)
  • Stage 3A and 3B construction started (2019)
  • Planning for Stages 3-6 started (2018)
  • Stage 1 and 2 completed (2017)
  • First lots released for sale (2016)
  • Stage 1 and 2 construction started (2015)
  • Development applications for Stages 1 and 2 approved (2014)
  • Concept plan approved (2013)
  • · Development applications submitted to Campbelltown City Council for Stages 1 and 2 (2013)

Community newsletter

Document Download
August 2024
Download
Remediation works fact sheet (June 2024)
Download
May 2024
Download
Notification of Stage 5 works (May 2024)
Download
View more

Visit our Sales Centre

Visit our Sales Centre, at the corner of Clydesdale Drive and Badgally Road, Claymore. 

Corner of Clydesdale Drive and Badgally Road, Claymore

(02) 9841 8765

hillcroft@landcom.nsw.gov.au

Rectangle 429

If you require the services of an interpreter, please contact the Translating and Interpreting Service on 131 450 and ask them to call Landcom on 02 9841 8600. The interpreter will then assist you with the translation.

Was this page helpful?